| 1 | \section{Requirements to start full GRB observations} | 
|---|
| 2 |  | 
|---|
| 3 | In the previous sessions we described the status and tasks we still plan to do | 
|---|
| 4 | in order to complete the GRB Alarm System. | 
|---|
| 5 | At the same time, also the other different subsystems of the MAGIC telescope have | 
|---|
| 6 | to implement and test strategies for the GRB survey. | 
|---|
| 7 |  | 
|---|
| 8 | \par | 
|---|
| 9 |  | 
|---|
| 10 | We strongly push the responsible persons of the Drive-, Camera-, AMC- and Central | 
|---|
| 11 | Control subsystems to fulfill the criteria defined in~\cite{design}. We suggest | 
|---|
| 12 | to make a one week shift where the experts meet and test the GRB | 
|---|
| 13 | strategies. In order to avoid good observation time we suggest to make the shift | 
|---|
| 14 | during a Moon period. This shift should take place, in arrangement with the | 
|---|
| 15 | different subsystem managers, before April this year. The time limitation is | 
|---|
| 16 | based on the moment when SWIFT will start to work fully automatically and send | 
|---|
| 17 | alerts in real time to the ground stations. | 
|---|
| 18 | \par | 
|---|
| 19 |  | 
|---|
| 20 | We present now a list of tasks which are crucial for the GRB survey: | 
|---|
| 21 |  | 
|---|
| 22 | \par | 
|---|
| 23 |  | 
|---|
| 24 | \begin{itemize} | 
|---|
| 25 | \item {\bf Fast slewing:}\ | 
|---|
| 26 |  | 
|---|
| 27 | One of the most important issues is to implement and test the fast slewing capability | 
|---|
| 28 | of the telescope. In particular, the communication between CC and Cosy has still to be implemented for | 
|---|
| 29 | the case of fast movements. | 
|---|
| 30 |  | 
|---|
| 31 | \item {\bf Use of look-up tables:}\ | 
|---|
| 32 |  | 
|---|
| 33 | The use of look-up tables to correct the mirror focus during the slewing to the GRB | 
|---|
| 34 | coordinates is desirable. In the alert situation it is a waste of time if we would have to | 
|---|
| 35 | close the camera lids and carry out the full laser adjustment ($\sim 5$~min) before starting the observation. | 
|---|
| 36 | The reproducibility of the focus with the use of look-up tables has to be proven. | 
|---|
| 37 | In case of using lookup-tables during the slewing, it is necessary to change the protocol between the AMC and CC. | 
|---|
| 38 |  | 
|---|
| 39 | \item {\bf Behaviour of the camera during Moon:}\ | 
|---|
| 40 |  | 
|---|
| 41 | It has still to be checked what happens when the telescope points directly at the Moon while | 
|---|
| 42 | slewing toward a new position. The GRB Alert System prevents a burst closer than $30^\circ$ | 
|---|
| 43 | from the Moon to be pointed. | 
|---|
| 44 | However, it can happen that during the movement of the telescope the Moon will enter the FoV. | 
|---|
| 45 | In this case the HV of the PMTs will be reduced automatically and will not increase fast enough for the | 
|---|
| 46 | GRB observation. | 
|---|
| 47 | \end{itemize} | 
|---|
| 48 |  | 
|---|